February 1, 2019. Charley and I selected Tumble Moon’s bedding and some other fabrics from Mary Cates and Co. I was going for a simple rustic look like the Shaker style. Click the link below to see my inspiration photo.
Tag: Charley McKenney
Tumble Moon (Update 12)
May 2, 2018. I, Charley (architect), and Michael Parkey (landscape architect) met with multiple contractors at Tumble Moon in Saint Jo. It was a very long hard day. One of the contractors was the son of my general contractor, who has been undergoing extensive treatment for some serious illnesses. The son had been brought into the company to take care of things while his dad took care of his health. He had not met any of us and had to be filled in and brought up to speed which included going over the building of the side-door deck and steps and of course, the front porch’s elaborate system of steps and terraces. This was at least the third time, and hopefully the last, going over all this. I had construction documents drawn up to give Jacob, the general contractor’s son. He’s an engineer, so this was helpful.
Tumble Moon (Update 11)
This update is three and a half months late. Not much has occurred since this visit at the very end of October, because we’ve been on hold waiting for the septic system to be installed. And the reason for this delay was because of a major communication hiccup between contractors. The electrical trench and water pipe were installed right through the area where the septic field was suppose to be. So we all got together and discussed the pros and cons of viable placement options. Meaning… Once we agreed on the new location, new plans had to be redrawn and then permitted. Then the holidays happened, folks got sick, and the weather has been working against us. Long story short, three point five months later, the septic system has now been installed, but we’re waiting on the electrician to provide an electrical outlet in the pump house so we can plug in a heat lamp to keep the water from freezing and bursting pipes.
Tumble Moon (Update 10)
Here’s the progress as of Friday, September 15. The interiors have now been painted, the stair bannisters and counter tops are now in place, the water pipes are now connected to the well, and the house now has electricity. The tiling of the kitchen backsplash, bathrooms, and hearth had just began on the day I was there, and as of last week, Friday, October 6, all of this had been completed. This week, the light fixtures and door hardware, which are there and waiting, should be installed, and I will also be ordering all the appliances. Unfortunately, we’ll have to wait to place them until after the floor has been stained. The septic system should also be installed soon. The poor guy who will be doing this had to wait until all the water pipe and electrical trenching had been completed.
Tumble Moon (Update 8)
Here’s the progress as of Thursday, June 29. All the cabinetry had been installed, and the carpenter was informed on how to proceed with the trim work. The painter applied floor stain samples and interior paint colors for our approval. Unfortunately the floor stain was not at all what it was suppose to be, but the selected interior wall, ceiling, and window/door trim colors were perfect. The design and materials for the front steps and the descent down to the driveway were finalized, and one final site survey was done. I know I’m forgetting several somethings, but the following photographs should illustrate how far things have progressed.
Tumble Moon (Update 6)
Last week we all met at Tumble Moon to go over wood floor options, exterior colors, and interior paint, tile, and countertop colors. And most importantly to work out the site’s grading and how to develop the approach to the front of the house, which I will cover in a future post.
Tumble Moon (Update 5)
The house is now a structural reality. Charley McKenney and I met the general contractor Pat Fuhrmann today along with his subs to go over the custom cabinetry and the electrical needs for my tiny house. It was perfect spring weather with an incredible cross breeze blowing through the window and door openings. And the views from the windows are even more spectacular than I had imagined. Again, I should have taken my fancy camera with a zoom lens, but instead shot the following photos with my iPhone.
Tumble Moon (Update 4)
With the foundation complete, I and my architect, Charley McKenney, took Eco Friends Pest Control out to Tumble Moon to do the first phase of the termite treatment. The second and final treatment will have to wait until after all construction and exterior grading have been completed.
Tumble Moon (Update 2)
Design Development. We (Charley McKenney and I) have now moved from the schematic phase to the design development phase. Actually we’re further along and are now way into the construction document phase, but this post is about the design development and includes all the interior elevations. You know… the fun stuff. Once you have clicked over to the entire post, please remember that by clicking on an image, you will see a much larger version. While you’re in the large version mode you can click the right arrow which will take you to the next drawing. This way you don’t have to exit this mode in order to get to the next image, but you will need to exit in order to read the captions.
Tumble Moon (Update 1)
I finally decided on a name for my new piece of heaven, Tumble Moon. It’s the name of a Texas Dude ranch in an old campy film called Lightning Strikes Twice (1951). It seems that all the other name combinations that might describe my property’s uniqueness were already spoken for by multiple apartment complexes.